[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148452":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148452,802,1,"单选题","以下选项中关于热拌沥青混合料路面接缝说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将已摊铺混合料留下部分暂不碾压，然后跨缝压实的做法属于冷接缝",false,{"key":16,"text":17,"correct":18},"B","采用梯队作业摊铺时应选用热接缝",true,{"key":20,"text":21,"correct":14},"C","高等级道路各层的横向接缝应采用平接缝",{"key":23,"text":24,"correct":14},"D","其他等级的道路各层的横向接缝可采用平接缝","2020\u002F2019教材P32 采用梯队作业方式摊铺时应选用热接缝。 A:属于热接缝 C:正确:高等级路面的表面层横缝采用垂直的平接缝，以下各层和各等级的道路可采用斜接缝。 D:其他等级的路面，则应采用斜接缝。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]