[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148415,802,1,"单选题","填土路基填土至最后一层时，应按设计断面、高程控制()，并及时碾压修整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","填土厚度",true,{"key":16,"text":17,"correct":18},"B","填土坡度",false,{"key":20,"text":21,"correct":18},"C","填土宽度",{"key":23,"text":24,"correct":18},"D","填土长度","2020教材P17 \u002F 2019教材P16 （6）路基填方高度应按设计标高增加预沉量值。填土至最后一层时，应按设计断面、高程控制填土厚度并及时碾压修整。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]