[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148395,802,1,"单选题","以下选项中不属于城镇道路路基工程施工流程的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","路基施工",false,{"key":16,"text":17,"correct":14},"B","附属构筑物施工",{"key":19,"text":20,"correct":21},"C","基层施工",true,{"key":23,"text":24,"correct":14},"D","准备工作","2020\u002F2019教材P16 三）基本流程：1.准备工作2.附属构筑物3.路基（土、石方）施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]