[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148349,802,1,"单选题","下列关于柔性管道回填施工做法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","回填之前，现场需要做试验段，长度应为一个井段或不少于100m",true,{"key":16,"text":17,"correct":18},"B","管内径大于800mm 的柔性管道，回填施工中应在管内设竖向支撑",false,{"key":20,"text":21,"correct":18},"C","管道回填时间宜在一昼夜中气温最低时段，从管道两侧同时回填，同时夯实",{"key":23,"text":24,"correct":18},"D","管道半径以下回填时应采取防止管道上浮、位移的措施","现场试验段长度应为一个井段或不少于50m。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]