[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148331":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148331,802,1,"单选题","下列说法中，不属于控制性进度计划内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","年度和季度施工计划是总进度的重要节点目标",false,{"key":16,"text":17,"correct":14},"B","总工期跨越三个年度的进度计划",{"key":19,"text":20,"correct":14},"C","按年度计划编制季度施工计划",{"key":22,"text":23,"correct":24},"D","发现进度计划受到干扰时应及时采取调整措施",true,"本题考查的是施工进度计划调控措施。选项D属于进度调整的内容。教材P341。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]