[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148330,802,1,"单选题","质量管理与控制持续改进中，实施纠正措施的结果应由（ ）验证并记录。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量负责人",false,{"key":16,"text":17,"correct":18},"B","项目技术负责人",true,{"key":20,"text":21,"correct":14},"C","项目负责人",{"key":23,"text":24,"correct":14},"D","生产负责人","本题考查的是施工质量控制要点。实施纠正措施的结果应由施工项目技术负责人验证并记录。教材P350。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]