[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148315,802,1,"单选题","单位工程完工后，（ ）组织进行竣工预验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","业主代表",{"key":19,"text":20,"correct":21},"C","总监",true,{"key":23,"text":24,"correct":14},"D","设计单位","本题考查的是工程竣工验收要求。单位工程完工后，施工单位应组织有关人员进行自检，总监理工程师应组织各专业监理工程师对工程质量进行竣工预验收，对存在的问题，应由施工单位及时整改。教材P455。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]