[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148268,802,1,"单选题","HDPE膜试验性焊接表述错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","试验性焊接完成后，割下3块试块，测试撕裂强度和抗剪强度",false,{"key":16,"text":17,"correct":14},"B","当任一试块没有通过撕裂和抗剪测试时，试验性焊接应全部重做",{"key":19,"text":20,"correct":21},"C","每一片膜要在铺设的当天进行焊接，即使底部接驳焊缝也不例外",true,{"key":23,"text":24,"correct":14},"D","填写HDPE膜试样焊接记录表，经现场监理和技术负责人签字后存档","本题考查的是聚乙烯（HDPE）膜防渗层施工技术。选项C说法错误，且属于HDPE膜生产焊接的内容。正确说法为“每一片HDPE膜要在铺设的当天进行焊接，如果采取适当的保护措施可防止雨水进入下面的地表，底部接驳焊缝，可以例外。”教材P255。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]