[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148267,802,1,"单选题","HDPE膜铺设及施工说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","铺设应一次展开到位，不宜展开后再拖动",false,{"key":16,"text":17,"correct":14},"B","车辆不得直接在HDPE膜上碾压",{"key":19,"text":20,"correct":21},"C","铺设总体顺序一般为先场底后边坡，边坡铺设时应将卷材自上而下滚铺",true,{"key":23,"text":24,"correct":14},"D","铺设区域内禁止使用火柴、打火机和化学溶剂或类似的物品","本题考查的是聚乙烯（HDPE）膜防渗层施工技术。填埋场HDPE膜铺设总体顺序一般为“先边坡后场底”，在铺设时应将卷材自上而下滚铺。教材P254。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]