[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148244":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148244,802,1,"单选题","综合管廊断面布置错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","蒸汽热力管道应在独立舱内敷设",false,{"key":16,"text":17,"correct":14},"B","110KV电力电缆不应与通信电缆同侧布置",{"key":19,"text":20,"correct":21},"C","给水管道与热力管道同侧布置时，热力管道宜布置在给水管道下方",true,{"key":23,"text":24,"correct":14},"D","排水管道应采取分流制，污水宜设置在管廊底部","本题考查的是综合管廊工程结构类型和特点。选项C错误，给水管道与热力管道同侧布置时，给水管道宜布置在热力管道下方。教材P245。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]