[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148234,802,1,"单选题","沉井垫层铺设施工错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","砂垫层分布在刃脚中心线的两侧范围，应考虑方便拆除垫木",false,{"key":16,"text":17,"correct":14},"B","砂垫层宜采用中粗砂",{"key":19,"text":20,"correct":21},"C","垫木铺设时，每根垫木的长度中心不得与刃脚底面中心线重合，以方便抽除垫木",true,{"key":23,"text":24,"correct":14},"D","沉井刃脚采用砖模时，砖模表面可采用水泥砂浆抹面，并涂隔离剂","本题考查的是沉井准备工作。选项C，每根垫木的长度中心应与刃脚底面中心线重合。教材P196。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]