[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148229,802,1,"单选题","污水处理厂试运行基本程序有（1）单机试车；（2）设备机组充水试验；（3）设备机组负荷试运行；（4）设备机组自动开停机试运行；（5）设备机组空载试运行。下面顺序正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","（1）→（2）→（3）→（4）→（5）",false,{"key":16,"text":17,"correct":14},"B","（1）→（2）→（4）→（3）→（5）",{"key":19,"text":20,"correct":14},"C","（2）→（1）→（4）→（3）→（5）",{"key":22,"text":23,"correct":24},"D","（1）→（2）→（5）→（3）→（4）",true,"本题考查的是给水与污水处理厂试运行。污水处理厂试运行基本程序：单机试车、设备机组充水试验、设备机组空载试运行、设备机组负荷试运行、设备机组自动开停机试运行。教材P188。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]