[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148203,802,1,"单选题","浅埋暗挖法施工方法表述错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初期支护必须从上向下施工",false,{"key":16,"text":17,"correct":14},"B","二次衬砌模筑必须通过变形量测确认基本稳定后才能施工",{"key":19,"text":20,"correct":14},"C","二衬必须从下向上施工",{"key":22,"text":23,"correct":24},"D","二衬允许先拱后墙施工",true,"本题考查的是暗挖施工方法比较与选择。初期支护必须从上向下施工，二次衬砌模筑必须通过变形量测确认初期支护结构基本稳定时，才能施工，而且必须从下往上施工，绝不允许先拱后墙施工。教材P105。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]