[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148195,802,1,"单选题","沉入桩终止锤击的控制应以控制桩端（ ）为主。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计标高",true,{"key":16,"text":17,"correct":18},"B","承载力",false,{"key":20,"text":21,"correct":18},"C","实际标高",{"key":23,"text":24,"correct":18},"D","贯入度","桩终止锤击的控制应视桩端土质而定，一般情况下以控制桩端设计标高为主，贯入度为辅。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]