[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148188,802,1,"单选题","箱涵顶进挖运土方错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按设计坡度开挖，每次开挖进尺0.4～0.8m",false,{"key":16,"text":17,"correct":14},"B","顶板切土，侧刃脚切土及底板前清土须人工配合",{"key":19,"text":20,"correct":14},"C","两侧欠挖50mm，钢刃脚切土前进",{"key":22,"text":23,"correct":24},"D","列车通过时可继续机械挖土，但人员应撤离",true,"本题考查的是管涵施工技术。列车通过时严禁继续挖土。教材P94。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]