[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148187,802,1,"单选题","下面关于箱涵顶进工艺流程正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作坑开挖→工程降水→后背制作→滑板制作→铺设润滑隔离层→箱涵制作",false,{"key":16,"text":17,"correct":14},"B","工程降水→后背制作→工作坑开挖→滑板制作→铺设润滑隔离层→箱涵制作",{"key":19,"text":20,"correct":14},"C","工程降水→工作坑开挖→后背制作→铺设润滑隔离层→滑板制作→箱涵制作",{"key":22,"text":23,"correct":24},"D","工程降水→工作坑开挖→后背制作→滑板制作→铺设润滑隔离层→箱涵制作",true,"本题考查的是箱涵顶进施工技术。工艺流程：工程降水→工作坑开挖→后背制作→滑板制作→铺设润滑隔离层→箱涵制作。教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]