[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148182,802,1,"单选题","下列关于沉入桩施工的说法中错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先深后浅",false,{"key":16,"text":17,"correct":14},"B","先大后小",{"key":19,"text":20,"correct":14},"C","由中间向两端或向四周施打",{"key":22,"text":23,"correct":24},"D","先短后长",true,"本题考查的是沉入桩基础。沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计标高，宜先深后浅；根据桩的规格，宜先大后小，先长后短。教材P70。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]