[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148148,802,1,"单选题","内径大于1000mm 的现浇钢筋混凝土管渠，预（自）应力混凝土管、预应力钢筒混凝土管试验管段注满水后浸泡时间应不少于（ ）h。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24",false,{"key":16,"text":17,"correct":18},"B","48",true,{"key":20,"text":21,"correct":14},"C","72",{"key":23,"text":24,"correct":14},"D","12","内径大于1000mm 不少于72h，内径小于1000mm 不少于24h。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]