[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148127,802,1,"单选题","（2010 年真题 广东海南）预应力张拉施工应由工程项目（ ）主持。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","施工负责人",{"key":19,"text":20,"correct":21},"C","技术负责人",true,{"key":23,"text":24,"correct":14},"D","质检负责人","预应力张拉施工的人员控制包括三方面：（1）承担预应力施工的单位应具有相应的施工资质；（2）预应力张拉施工应由工程项目技术负责人主持；（3）张拉作业人员应经培训考核，合格后方可上岗。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]