[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148122,802,1,"单选题","（2019 年真题）冬期施工质量控制要求的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","粘层、透层、封层严禁冬期施工",false,{"key":16,"text":17,"correct":14},"B","水泥混凝土拌合料温度应不高于35℃",{"key":19,"text":20,"correct":21},"C","水泥混凝土拌合料可加防冻剂、缓凝剂，搅拌时间适当延长",true,{"key":23,"text":24,"correct":14},"D","水泥混凝土板弯拉强度低于1MPa 或抗压强度低于5MPa 时，不得受冻","P356。（四）沥青混凝土面层（1）城市快速路、主干路的沥青混合料面层严禁冬期施工。次干路及其以下道路在施工温度低于5℃时，应停止施工。（2）粘层、透层、封层严禁冬期施工。（五）水泥混凝土面层（1）搅拌站应搭设工棚或其他挡风设备，搅拌机出料温度不得低于10℃，摊铺混凝土温度不应低于5℃。（2）施工中应根据气温变化采取保温防冻措施。当连续5 昼夜平均气温低于-5℃，或最低气温低于-15℃时，宜停止施工。（3）混凝土拌合料温度应不高于35℃。拌合物中不得使用带有冰雪的砂、石料，可加防冻剂、早强剂，搅拌时间适当延长。（4）混凝土板弯拉强度低于1MPa 或抗压强度低于5MPa 时，不得受冻。（5）混凝土板浇筑前，基层应无冰冻、不积冰雪，摊铺混凝土时气温不低于5℃。（6）尽量缩短各工序时间，快速施工。成型后，及时覆盖保温层，减缓热量损失，使混凝土的强度在其温度降到0℃前达到设计强度。（7）养护时间不宜少于21d。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]