[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148117,802,1,"单选题","（2017 年真题）下图双代号网络图中，下部的数字表示的含义是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作持续时间",true,{"key":16,"text":17,"correct":18},"B","施工顺序",false,{"key":20,"text":21,"correct":18},"C","节点排序",{"key":23,"text":24,"correct":18},"D","工作名称","",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]