[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148114,802,1,"单选题","（2019 年真题）施工组织设计的核心部分是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管理体系",false,{"key":16,"text":17,"correct":14},"B","质量、安全保证计划",{"key":19,"text":20,"correct":14},"C","技术规范及检验标准",{"key":22,"text":23,"correct":24},"D","施工方案",true,"（四）施工方案及技术措施（1）施工方案是施工组织设计的核心部分，主要包括拟建工程的主要分项工程的施工方法、施工机具的选择、施工顺序的确定，还应包括季节性措施、四新技术措施以及结合工程特点和由施工组织设计安排的、根据工程需要采取的相应方法与技术措施等方面的内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]