[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148110":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148110,802,1,"单选题","（2010 年真题）根据《建设工程清单计价规范》，分部分项工程量清单综合单价由（ ）组成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工费、材料费、机械费、管理费、利润",true,{"key":16,"text":17,"correct":18},"B","直接费、间接费、措施费、管理费、利润",false,{"key":20,"text":21,"correct":18},"C","直接费、间接费、规费、管理费、利润",{"key":23,"text":24,"correct":18},"D","直接费、安全文明施工费、规费、管理费、利润","综合单价法是指分部分项工程单价综合了直接工程费以外的多项费用，依据综合内容不同，还可分为全费用综合单价和部分费用综合单价。我国目前推行的建设工程工程量清单计价其实就是部分费用综合单价，单价中未包括措施费、规费和税金。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]