[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148100,802,1,"单选题","（2017 年真题）关于施工测量的说法,错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","规划批复和设计文件是施工测量的依据",false,{"key":16,"text":17,"correct":14},"B","施工测量贯穿于工程实施的全过程",{"key":19,"text":20,"correct":21},"C","施工测量应遵循“由局部到整体,先细部后控制”的原则",true,{"key":23,"text":24,"correct":14},"D","综合性工程使用不同的设计文件时,应进行平面控制网联测","考查施工测量",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]