[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148065":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148065,802,1,"单选题","（2018 年真题 广东海南）给水管道水压试验时，向管道内注水浸泡的时间，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有水泥砂浆衬里的球墨铸铁管不少于12h",false,{"key":16,"text":17,"correct":18},"B","有水泥砂浆衬里的钢管不少于24h",true,{"key":20,"text":21,"correct":14},"C","内径不大于1000mm 的自应力混凝土管不少于36h",{"key":23,"text":24,"correct":14},"D","内径大于1000mm 的自应力混凝土管不少于48h","A 项：有水泥砂浆衬里的球墨铸铁管浸泡时间不少于24h。C 项：内径不大于1000mm 的自应力混凝土管浸泡时间不少于48h。D 项：内径大于1000mm 的自应力混凝土管浸泡时间不少于72h。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]