[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148064,802,1,"单选题","（2018 年真题）关于沟槽开挖与支护相关规定的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","机械开挖可一次挖至设计高程",false,{"key":16,"text":17,"correct":14},"B","每次人工开挖槽沟的深度可达3m",{"key":19,"text":20,"correct":21},"C","槽底土层为腐蚀性土时，应按设计要求进行换填",true,{"key":23,"text":24,"correct":14},"D","槽底被水浸泡后，不宜采用石灰土回填","A 项应为：机械挖槽时槽底预留200～300mm 土层，由人工开挖至设计高程，整平。B 项应为：人工开挖沟槽的槽深超过3m 时应分层开挖，每层的深度不超过2m。D 项应为：槽底不得受水浸泡或受冻，槽底局部扰动或受水浸泡时，宜采用天然级配砂砾石或石灰土回填。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]