[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148061,802,1,"单选题","（2019 年真题）关于沟槽开挖的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","机械开挖时，可以直接挖至槽底高程",false,{"key":16,"text":17,"correct":18},"B","槽底土层为杂填土时，应全部挖除",true,{"key":20,"text":21,"correct":14},"C","沟槽开挖的坡率与沟槽的深度无关",{"key":23,"text":24,"correct":14},"D","无论土质如何，槽壁必须垂直平顺","沟槽开挖与支护（一）分层开挖及深度（1）人工开挖沟槽的槽深超过3m 时应分层开挖，每层的深度不超过2m。（2）人工开挖多层沟槽的层间留台宽度：放坡开槽时不应小于0.8m；直槽时不应小于0.5m；安装井点设备时不应小于1.5m。（3）采用机械挖槽时，沟槽分层的深度按机械性能确定。（二）沟槽开挖规定（1）槽底原状地基土不得扰动，机械开挖时槽底预留200～300mm 土层，由人工开挖至设计高程，整平。（2）槽底不得受水浸泡或受冻，槽底局部扰动或受水浸泡时，宜采用天然级配砂砾石或石灰土回填；槽底扰动土层为湿陷性黄土时，应按设计要求进行地基处理。（3）槽底土层为杂填土、腐蚀性土时，应全部挖除并按设计要求进行地基处理。（4）槽壁平顺，边坡坡度符合施工方案的规定。（5）在沟槽边坡稳固后设置供施工人员上下沟槽的安全梯。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]