[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148059,802,1,"单选题","（2013 年真题）采用排水下沉施工的沉井封底措施中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","封底前设置泄水井",false,{"key":16,"text":17,"correct":18},"B","封底前停止降水",true,{"key":20,"text":21,"correct":14},"C","封底前，井内应无渗漏水",{"key":23,"text":24,"correct":14},"D","封底前用石块将刃脚垫实","封底前应设置泄水井，底板混凝土强度达到设计强度等级且满足抗浮要求时，方可封填泄水井、停止降水。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]