[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148057,802,1,"单选题","（2018 年真题 广东海南）在预制构件吊装方案编制中，吊装程序和方法应写入（ ）中。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程概况",false,{"key":16,"text":17,"correct":14},"B","质量保证措施",{"key":19,"text":20,"correct":14},"C","安全保证措施",{"key":22,"text":23,"correct":24},"D","主要技术措施",true,"预制构件吊装方案应包括以下内容：（1）工程概况，包括施工环境、工程特点、规模、构件种类数量、最大构件自重、吊距以及设计要求、质量标准。（2）主要技术措施，包括吊装前环境、材料机具与人员组织等准备工作、吊装程序和方法、构件稳固措施，不同气候施工措施等。（3）吊装进度计划。（4）质量安全保证措施，包括管理人员职责，检测监控手段，发现不合格的处理措施以及吊装作业记录表格等安全措施。（5）环保、文明施工等保证措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]