[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148056,802,1,"单选题","（2018 年真题）关于装配式预应力混凝土水池预制构件安装的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","曲梁应在跨中临时支撑，待上部混凝土达到设计强度的50%，方可拆除支撑",false,{"key":16,"text":17,"correct":14},"B","吊绳与预制构件平面的交角不小于35°",{"key":19,"text":20,"correct":21},"C","预制曲梁宜采用三点吊装",true,{"key":23,"text":24,"correct":14},"D","安装的构件在轴线位置校正后焊接","A 项应为：曲梁应在梁的跨中临时支撑，待上部二期混凝土达到设计强度的75%及以上时，方可拆除支撑。B 项应为：吊绳与预制构件平面的交角不应小于45°。D 项应为：安装的构件，必须在轴线位置及高程进行校正后焊接或浇筑接头混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]