[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148033,802,1,"单选题","（2019 年真题）沿隧道轮廓采取自上而下一次开挖成形，按施工方案一次进尺并及时进行初期支护的方法称为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","正台阶法",false,{"key":16,"text":17,"correct":14},"B","中洞法",{"key":19,"text":20,"correct":21},"C","全断面法",true,{"key":23,"text":24,"correct":14},"D","环形开挖预留核心土法","全断面开挖法采取自上而下一次开挖成型，沿着轮廓开挖，按施工方案一次进尺并及时进行初期支护。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]