[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148030,802,1,"单选题","（2014 年真题关于隧道全断面暗挖法施工的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可减少开挖对围岩的扰动次数",false,{"key":16,"text":17,"correct":14},"B","围岩必须有足够的自稳能力",{"key":19,"text":20,"correct":14},"C","自上而下一次开挖成形并及时进行初期支护",{"key":22,"text":23,"correct":24},"D","适用于地表沉降难于控制的隧道施工",true,"全断面开挖法的优点是可以减少开挖对围岩的扰动次数，有利于围岩天然承载拱的形成，工序简便，缺点是对地质条件要求严格，围岩必须有足够的自稳能力。故D 说法错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]