[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148025,802,1,"单选题","（2020年真题）盾构接收施工，工序可分为①洞门凿除、②到达段掘进、③接收基座安装与固定、④洞门密封安装、⑤盾构接收，施工程序正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-③-④-②-⑤",true,{"key":16,"text":17,"correct":18},"B","①-②-③-④-⑤",false,{"key":20,"text":21,"correct":18},"C","①-④-②-③-⑤",{"key":23,"text":24,"correct":18},"D","①-②-④-③-⑤","P147-150 盾构接收一般按下列程序进行：洞门凿除→接收基座的安装与固定→洞门密封安装→到达段掘进→盾构接收。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]