[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148000,802,1,"单选题","（2016 年真题）关于钢梁施工的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人行天桥钢梁出厂前可不进行试拼装",false,{"key":16,"text":17,"correct":14},"B","多节段钢梁安装时，应全部节段安装完成后再测量其位置、标高和预拱度",{"key":19,"text":20,"correct":14},"C","施拧钢梁高强螺栓时，最后应采用木棍敲击拧紧",{"key":22,"text":23,"correct":24},"D","钢梁顶板的受压横向对接焊缝应全部进行超声波探伤检验",true,"A 项错在“钢梁出厂前必须进行试拼装，并应按设计和有关规范的要求验收”。B 项错在“钢梁安装过程中，每完成一节段应测量其位置、标高和预拱度”。C 项错在“施拧时，不得采用冲击拧紧和间断拧紧”。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]