[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1147997,802,1,"单选题","（2019 年真题）关于装配式预制混凝土梁存放的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预制梁可直接支承在混凝土存放台座上",false,{"key":16,"text":17,"correct":18},"B","构件应按其安装的先后顺序编号存放",true,{"key":20,"text":21,"correct":14},"C","多层叠放是，各层垫木的位置在竖直线上应错开",{"key":23,"text":24,"correct":14},"D","预应力混凝土梁存放时间最长为6 个月","P76。（三）构件的存放（1）存放台座应坚固稳定、且宜高出地面200mm 以上。存放场地应有相应的防排水设施，并应保证梁、板等构件在存放期间不致因支点沉陷而受到损坏。（2）梁、板构件存放时，其支点应符合设计规定的位置，支点处应采用垫木和其他适宜的材料支承，不得将构件直接支承在坚硬的存放台座上；存放时混凝土养护期未满的，应继续洒水养护。（3）构件应按其安装的先后顺序编号存放，预应力混凝土梁、板的存放时间不宜超过3 个月，特殊情况下不应超过5 个月。（4）当构件多层叠放时，层与层之间应以垫木隔开，各层垫木的位置应设在设计规定的支点处，上下层垫木应在同一条竖直线上；叠放高度宜按构件强度、台座地基承载力、垫木强度以及堆垛的稳定性等经计算确定。大型构件宜为2 层，不应超过3 层；小型构件宜为6~10 层。（5）雨季和春季融冻期间，应采取有效措施防止因地面软化下沉而造成构件断裂及损坏。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]