[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1147995,802,1,"单选题","（2011 年真题）桥梁施工时合拢段说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合拢前应观测气温变化与梁端高程及悬臂端间距的关系",false,{"key":16,"text":17,"correct":14},"B","合拢段的混凝土强度宜提高一级",{"key":19,"text":20,"correct":14},"C","合拢段长度宜为2m",{"key":22,"text":23,"correct":24},"D","气温最高时浇筑",true,"桥梁施工时，合龙宜在一天中气温最低时进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]