[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147977":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1147977,802,1,"单选题","（2014 年真题关于预应力施工的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预应力筋实际伸长值与理论伸长值之差应控制在±6%以内",false,{"key":16,"text":17,"correct":18},"B","预应力筋张拉的目的是减少孔道摩阻损失的影响",true,{"key":20,"text":21,"correct":14},"C","后张法曲线孔道的波峰部位应留排气孔",{"key":23,"text":24,"correct":14},"D","曲线预应力筋宜在两端张拉","张拉前应根据设计要求对孔道的摩阻损失进行实测，以便确定张拉控制应力值，并确定预应力筋的理论伸长值。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]