[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1147975,802,1,"单选题","（2015 年真题）关于桥面防水施工质量验收规定的说法，错误的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","桥面防水施工应符合设计文件要求",false,{"key":16,"text":17,"correct":14},"B","从事防水施工检查验收工作的人员应具备规定的资格",{"key":19,"text":20,"correct":14},"C","防水施工验收应在施工单位自行检查评定基础上进行",{"key":22,"text":23,"correct":24},"D","防水施工验收应在桥面铺装层完成后一次性进行",true,"本题考查的是桥面防水质量验收，桥面防水质量验收，一般规定：1.桥面防水施工应符合设计文件的要求。2.从事防水施工验收检验工作的人员应具备规定的资格。3.防水施工验收应在施工单位自行检查评定的基础上进行。4.施工验收应按施工顺序分阶段验收。5.检测单元应符合的要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]