[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1147967,802,1,"单选题","（2018 年真题 广东海南）关于沥青混合料人工摊铺施工的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","路面狭窄部分，可采用人工摊铺作业",false,{"key":16,"text":17,"correct":18},"B","卸料点距摊铺点较远时，可扬锹远甩",true,{"key":20,"text":21,"correct":14},"C","半幅施工时，路中一侧宜预先设置挡板",{"key":23,"text":24,"correct":14},"D","边摊铺边整平，严防集料离析","B 项应为“摊铺时应扣锹布料，不得扬锹远甩”。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]