[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147934":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147934,801,2,"多选题","金属非金属露天矿山施工中，必须事先制定施工安全措施、征得矿山运输和安全部门同意和批准的施工内容包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","横穿路基架设电线",true,{"key":16,"text":17,"correct":14},"B","跨越矿山铁路",{"key":19,"text":20,"correct":14},"C","靠近露天矿山铁路修建构筑物",{"key":22,"text":23,"correct":24},"D","大型设备穿越涵洞",false,{"key":26,"text":27,"correct":24},"E","在矿山铁路两侧堆放物品","ABC","《金属非金属矿山安全规程》规定：靠近矿山铁路修筑建构筑物，跨越矿山铁路、横穿路基或桥涵架设电线和管道等，以及临时在矿山铁路附近施工，均应事先征得矿山运输和安全部门同意，并制定施工安全措施，经批准方可实施。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]