[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147902":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147902,801,2,"多选题","矿业工程技术档案的内容包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工组织管理技术档案",true,{"key":16,"text":17,"correct":14},"B","工程技术档案",{"key":19,"text":20,"correct":14},"C","工程进度交换图纸",{"key":22,"text":23,"correct":24},"D","招投标资料",false,{"key":26,"text":27,"correct":24},"E","合同管理资料","ABC","根据规定，矿业工程技术档案的内容包括： (1)施工组织管理技术档案 (2)工程技术档案 (3)工程进度交换图纸",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]