[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147892":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147892,801,2,"多选题","承包方提出的索赔事件的成立条件是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","事件可能造成承包人受到损失",false,{"key":16,"text":17,"correct":18},"B","事件已造成承包人受到损失",true,{"key":20,"text":21,"correct":18},"C","承包人的损失是发承包人的责任",{"key":23,"text":24,"correct":14},"D","承包人的损失是承包人的风险责任",{"key":26,"text":27,"correct":18},"E","承包人按规定提交了索赔意向书和索赔报告","BCE","索赔事件成立的条件是三方面，即(1)已经造成了的承包人损失，这个损失是指实际损失而非可能的损失或估计的损失；(2)损失的原因不属于承包人自己的行为责任和风险责任，如是承包人的行为造成或因为承包人承担的风险责任，则就不符合成立条件；(3)承包人按规定的程序要求提交了索赔意向书和索赔报告。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]