[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147889,801,2,"多选题","关于矿业工程合同变更的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","当合同一方认为条件不合适时，可以进行合同变更",false,{"key":16,"text":17,"correct":18},"B","合同变更的内容不能违法",true,{"key":20,"text":21,"correct":14},"C","合同变更的内容不能违反原合同",{"key":23,"text":24,"correct":18},"D","合同变更成立并不完全取消原来的债权、债务关系",{"key":26,"text":27,"correct":14},"E","合同变更必须在合同履行开始前进行","BD","合同变更一般需要有双方当事人的一致同意。答案A错误。合同变更属于合法行为。合同变更不得具有违法行为，违法协商变更的合同属于无效变更，不具有法律约束力。答案B正确。合同变更是对原合同部分内容的变更或修改。答案C错误。合同变更并没有完全取消原来的债权债务关系，合同变更涉及的未履行的义务没有消失，没有履行义务的一方仍须承担不履行义务的责任。答案D正确。合同变更的期限为合同订立之后到合同没有完全履行之前。答案E错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]