[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147877":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147877,801,2,"多选题","现行《建设工程工程量清单计价规范》GB50500--2013，对应配套的工程量计算规范包含（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","房屋建筑与装饰工程工程量计算规范",true,{"key":16,"text":17,"correct":18},"B","土地整理工程工程量计算规范",false,{"key":20,"text":21,"correct":14},"C","通用安装工程工程量计算规范",{"key":23,"text":24,"correct":14},"D","矿山工程工程量计算规范",{"key":26,"text":27,"correct":14},"E","园林绿化工程工程量计算规范","ACDE","现行《建设工程工程量清单计价规范》GB50500---2013，对应配套的工程量计算规范不包含土地整理工程工程量计算规范。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]