[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147876":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147876,801,2,"多选题","根据《建设工程工程清单计价规范》GB50500---2013，工程变更引起施工方案改变并使措施方案发生变化时，关于措施项目费调整的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","安全文明施工费按实际发生的措施项目，考虑承包人报价浮动因素进行调整",false,{"key":16,"text":17,"correct":18},"B","安全文明施工费按实际发生变化的措施项目调整，不得浮动",true,{"key":20,"text":21,"correct":18},"C","对单价计算的措施费，按实际发生变化的措施项目和已标价工程量清单项目确定单价",{"key":23,"text":24,"correct":14},"D","对总价计算的措施项目费一般不能进行调整",{"key":26,"text":27,"correct":14},"E","对总价计算的措施项目费，按实际发生变化的措施项目，不考虑承包人报价浮动因素进行调整","BC","工程变更引起施工方案改变并使措施方案发生变化时，安全文明施工费应按照实际发生变化的措施项目调整，不得浮动；采用单价计算的措施项目费，应按照实际发生变化的措施项目按照前述已标价工程量清单项目的规定确定单价；按总价(或系数)计算的措施项目费，按照实际发生变化的措施项目调整，但应考虑承包人报价浮动因素。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]