[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147872":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147872,801,2,"多选题","项目设计阶段影响工程投资的因素有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","总平面设计",true,{"key":16,"text":17,"correct":14},"B","工艺设计",{"key":19,"text":20,"correct":14},"C","建筑设计",{"key":22,"text":23,"correct":24},"D","矿产资源条件因素",false,{"key":26,"text":27,"correct":24},"E","建设地点的选择","ABC","项目设计阶段影响工程投资的因素有总平面设计、工艺设计和建筑设计。矿产资源条件因素和建设地点的选择属于项目决策阶段影响工程投资的因素。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]