[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147871":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147871,801,2,"多选题","制约矿业工程项目规模的因素有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","国家战略需要",true,{"key":16,"text":17,"correct":14},"B","资源的条件因素",{"key":19,"text":20,"correct":21},"C","装备条件因素",false,{"key":23,"text":24,"correct":14},"D","环境因素",{"key":26,"text":27,"correct":14},"E","技术和开发能力因素","ABDE","矿产资源为国家所有，它的开发涉及国家生产、社会发展、国防等国家重大事业，开发矿产都必须在国家计划之内，满足国家发展及整个国家利益的战略需要，不能由个人或企业随意决定(A)；资源开发的工程规模还必须根据资源条件，由地质勘探说明其开发的价值和可能性(B)；项目规模大小决定了对矿山装备的要求，而不是由装备条件来决定项目的规模(C)；矿业工程规模大小还和环境因素有关，这不仅是通常的环境条件(如交通、市场发展程度等)对规模的影响，还涉及矿业工程对环境的影响状况，当不允许对环境有较大影响时就会限制项目的规模(D)；项目规模还和开发能力有关，目前有的资源因为技术条件达不到而不能开发的情况也是存在的(E)。因此本题的答案应为A、B、D、E。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]