[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147870":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147870,801,2,"多选题","矿山项目决策阶段影响工程投资的因素有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","市场因素",true,{"key":16,"text":17,"correct":14},"B","建设的标准",{"key":19,"text":20,"correct":14},"C","建设地点",{"key":22,"text":23,"correct":14},"D","环境因素",{"key":25,"text":26,"correct":27},"E","总平面设计",false,"ABCD","市场因素、建设的标准、建设地点和环境因素均为矿山项目决策阶段影响工程投资的因素，总平面设计为项目设计阶段影响工程投资的因素。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]