[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147866":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147866,801,2,"多选题","常用的成本控制方法中，同时考虑成本与进度综合影响的方法是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","成本分析表法",false,{"key":16,"text":17,"correct":18},"B","工期成本同步分析法",true,{"key":20,"text":21,"correct":18},"C","挣值法",{"key":23,"text":24,"correct":14},"D","价值工程法",{"key":26,"text":27,"correct":14},"E","工期分析法","BC","常用的成本控制方法是题目的A、B、C、D选项。E选项不是用于成本控制；而其中工期成本同步分析法(B)是成本与进度对应的分析一种方法，挣值法(C)是通过比较进度成本与计划成本来分析、控制成本的方法。所以它们是直接与进度相关的成本控制方法。故答案应为B、C。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]