[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1147864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1147864,801,2,"多选题","矿业工程施工中、成本管理的基础工作是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","预算管理",true,{"key":16,"text":17,"correct":14},"B","定额管理",{"key":19,"text":20,"correct":14},"C","计量工作",{"key":22,"text":23,"correct":14},"D","原始记录",{"key":25,"text":26,"correct":27},"E","计划明确、赏罚分明",false,"ABCD","进行成本管理，必须有明确的依据，这些依据就是成本管理的基础工作，这些依据就是预算的要求、定额的控制、对实施情况的计量和真实情况的原始记录。费用计划和赏罚措施只是管理的一种方法，和基本依据不同。",{"id":6,"name":31,"category":32,"favorite":33},"一建矿业工程实务","建筑工程",0]